Fourth Plain Bus Rapid Transit
| Agency: | C-TRAN |
|---|---|
| Status: | Completed |
| FHWA Aid#: | FT14(005) |
| Project Type: | Transit |
| Description: | Construct Bus Rapid Transit primarily in mixed traffic, between downtown Vancouver and Westfield Vancouver Mall along Fourth Plain, Fort Vancouver, and downtown Vancouver Streets. |
| Termini: | Downtown Vancouver to Westfield Vancouver Mall |
| Project Length: | 6.00 miles |
| Completed: | January 8, 2017 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $4,000,000 | $5,000,000 | April 1, 2013 | May 28, 2013 |
| Right of Way | $1,038,000 | January 1, 2015 | September 10, 2015 | |
| Construction | $47,082,000 | February 1, 2016 | September 10, 2015 | |
| Total | $4,000,000 | $53,120,000 |