Project Showcase
Orchards Traffic Signal Optimization
| Agency: | Clark County |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 9906(040) |
| Project Type: | Transportation System Management and Operations |
| Description: | Signal hardware, interconnection and coordination of signal operation. Repair/upgrades to traffic detection. Addition of video cameras and permanent count stations at key locations. Connection of signal equipment to central county monitoring center. |
| Termini: | Orchards Area |
| Project Length: | 11.75 miles |
| Completed: | April 30, 2018 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $300,000 | $575,000 | March 1, 2013 | April 15, 2013 |
| Construction | $3,200,000 | $4,254,965 | November 1, 2014 | May 29, 2015 |
| Total | $3,500,000 | $4,829,965 |