Project Showcase
Transit Signal Priority-Highway 99
Agency: | C-TRAN |
---|---|
Status: | Design |
FHWA Aid#: | FT14(004) |
Project Type: | Transportation System Management and Operations |
Description: | Install and operate Transit Signal Priority at intersections along Highway 99 from Ross Street to the 99th Street Transit Center to include intersections west of Hwy 99 on 99th Street and south on 7th Avenue. |
Termini: | Ross Street to 7th Avenue |
Project Length: | 2.70 miles |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $120,000 | $150,000 | October 1, 2014 | May 15, 2014 |
Construction | $20,000 | $25,000 | March 1, 2015 | May 15, 2014 |
Total | $140,000 | $175,000 |
Project Photos