4th St and Pacific Highway Roundabout
Agency: | La Center |
---|---|
Status: | Completed |
FHWA Aid#: | D063(003) |
Project Type: | Reconstruction: No Added Capacity |
Description: | Intersection Improvement. Construct roundabout to meet LOS standard and pedestrian and traffic safety. |
Termini: | Pacific Highway @4th Street |
Project Length: | 0.12 miles |
Completed: | December 20, 2018 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $138,000 | $138,000 | May 1, 2014 | February 25, 2014 |
Construction | $692,000 | $2,040,000 | May 1, 2016 | December 14, 2017 |
Total | $830,000 | $2,178,000 |