18th Street Improvements - Segment 1B
| Agency: | Vancouver |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 4254(005) |
| Project Type: | Reconstruction: Add Capacity |
| Description: | Construct an access restricted 4 lane arterial with bike lanes and detached sidewalks. Project includes a frontage road on the north side between 126th Av. and 136th Av. |
| Termini: | Four Seasons Lane to NE 136th Avenue |
| Project Length: | 1.00 miles |
| Completed: | May 31, 2018 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $1,250,000 | January 1, 2009 | June 1, 2011 | |
| Right of Way | $1,284,434 | $3,237,000 | May 1, 2013 | April 16, 2013 |
| Construction | $5,515,566 | $11,000,000 | October 1, 2015 | September 9, 2016 |
| Total | $6,800,000 | $15,487,000 |