Aspen Avenue at 18th Street Crosswalk
Agency: | La Center |
---|---|
Status: | Completed |
FHWA Aid#: | D065(002) |
Project Type: | Pedestrian & Bicycle Facilities |
Description: | The project improves pedestrian safety across one of the City's busiest streets, by warning motorist when pedestrians and bicyclist are crossing Aspen Avenue. The project included crosswalk striping, a concrete access ramp, and advanced warning signals. |
Termini: | 18th Street to 18th Street |
Project Length: | 0.04 miles |
Completed: | November 1, 2014 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $3,600 | June 1, 2013 | October 1, 2013 | |
Construction | $27,700 | $31,025 | December 1, 2013 | May 2, 2014 |
Total | $27,700 | $34,625 |