78th Street Signal Optimization Project
| Agency: | Clark County |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 4392(015) |
| Project Type: | Transportation System Management and Operations |
| Description: | Signal hardware and interconnection. |
| Termini: | Hazel Dell Av. to St. Johns Rd. |
| Project Length: | 2.20 miles |
| Completed: | June 30, 2015 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $50,000 | $98,000 | February 1, 2011 | March 10, 2011 |
| Construction | $650,000 | $1,127,000 | January 1, 2012 | May 10, 2013 |
| Total | $700,000 | $1,225,000 |