Highway 99 Corridor Improvements
Agency: | Clark County |
---|---|
Status: | Under Construction |
FHWA Aid#: | 0099(129) |
Project Type: | Reconstruction: No Added Capacity |
Description: | Improve Highway 99 to a 4-lane principal arterial standard with raised medians and/or center turn lanes, bike lanes, sidewalks, and signal upgrades. Project will complete a corridor study to determine the best breaks in phasing of construction. |
Termini: | Highway 99/NE 99th St. Intersection |
Project Length: | 1.60 miles |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $1,000,000 | $1,894,000 | January 1, 2014 | November 20, 2013 |
Right of Way | $2,242,000 | January 1, 2015 | July 20, 2016 | |
Construction | $1,000,000 | $1,818,000 | January 1, 2021 | April 30, 2020 |
Total | $2,000,000 | $5,954,000 |