Project Showcase
Mill Plain TSP Phase II
| Agency: | C-TRAN |
|---|---|
| Status: | Completed |
| FHWA Aid#: | FT19(002) |
| Project Type: | Transportation System Management and Operations |
| Description: | Implement traffic signal priority on remaining intersections along Mill Plain and 164th Av. |
| Termini: | I-5 to 182nd Avenue |
| Project Length: | 9.30 miles |
| Completed: | October 1, 2023 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Construction | $195,500 | $262,500 | February 1, 2018 | May 3, 2019 |
| Total | $195,500 | $262,500 |