Mill Plain Boulevard Arrival on Green Improvement Project
| Agency: | Vancouver |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 4242(027) |
| Project Type: | Transportation System Management and Operations |
| Description: | Install signal equipment at multiple signalized intersections along Mill Plain to improve signal coordination along the corridor. |
| Termini: | Andresen Road to 155th Av. |
| Project Length: | 4.30 miles |
| Completed: | July 12, 2021 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Construction | $72,700 | $97,600 | February 1, 2017 | August 12, 2020 |
| Total | $72,700 | $97,600 |