SR-14 ATIS Infill: I-5 to Evergreen
| Agency: | WSDOT, SW Region |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 0014(083) |
| Project Type: | Transportation System Management and Operations |
| Description: | Install fiber optic communication link, data stations, and cameras. |
| Termini: | I-5 (MP 0) to Evergreen (MP 3.2) |
| Project Length: | 3.20 miles |
| Completed: | June 15, 2019 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $67,000 | $90,000 | October 1, 2016 | March 7, 2018 |
| Construction | $660,372 | $917,972 | August 1, 2018 | September 24, 2018 |
| Total | $727,372 | $1,007,972 |