Evergreen Highway Trail
| Agency: | Vancouver |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 4228(001) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Build bike and pedetrian trail along Evergreen Highway. |
| Termini: | Ellsworth to Weber Arboretum |
| Project Length: | 0.87 miles |
| Completed: | October 15, 2015 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $138,750 | $138,750 | September 1, 2010 | January 19, 2012 |
| Right of Way | $125,000 | $125,000 | February 1, 2011 | December 17, 2013 |
| Construction | $661,250 | $661,250 | September 1, 2011 | February 25, 2015 |
| Total | $925,000 | $925,000 |