Project Showcase
Columbia River Renaissance Trail Connection
| Agency: | Port of Vancouver |
|---|---|
| Status: | Completed |
| FHWA Aid#: | 2006(078) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Construct a pedestrian and bicycle path at the Port's Terminal 1 property. The trail will be ADA accessible and enhanced with security lighting, landscaping, benches, public art, wayfinding and interpretive signage. Project will require ground stabilization. |
| Termini: | Terminal 1 |
| Project Length: | 0.23 miles |
| Completed: | October 15, 2022 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Construction | $485,000 | $500,607 | January 1, 2019 | January 6, 2021 |
| Total | $485,000 | $500,607 |
Project Photos