Project Showcase
Jefferson Realignment Project
| Agency: | Vancouver |
|---|---|
| Status: | Under Construction |
| FHWA Aid#: | 4255(001) |
| Project Type: | Reconstruction: No Added Capacity |
| Description: | Realign intersections at 13th Street to create a single intersection. Reconstruct road to current standards, and continue Waterfront Multi-use trail to Mill Plain Blvd. |
| Termini: | W Evergreen Blvd to Mill Plain Blvd |
| Project Length: | 0.46 miles |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $975,000 | January 15, 2017 | January 15, 2017 | |
| Right of Way | $1,850,000 | January 15, 2020 | July 12, 2023 | |
| Construction | $5,040,000 | $11,675,000 | September 15, 2024 | September 6, 2024 |
| Total | $5,040,000 | $14,500,000 |
Project Photos
List of all projects.

