Project Showcase
Trail of the Gods
| Agency: | Stevenson |
|---|---|
| Status: | Completed |
| FHWA Aid#: | WA11(002) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Extends City of Stevenson's mutli-use trail system to its western city limit. |
| Termini: | Stevenson, Rock Creek Rd. to Mallicott Rd. |
| Project Length: | 0.45 miles |
| Completed: | May 14, 2015 |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $131,600 | July 1, 2011 | July 1, 2011 | |
| Construction | $66,400 | $773,100 | July 1, 2013 | May 21, 2014 |
| Total | $66,400 | $904,700 |