Project Showcase
I-5/NB Fourth Plain On Ramp-Ramp Meter
| Agency: | WSDOT, SW Region |
|---|---|
| Status: | Under Construction |
| FHWA Aid#: | 0051(318) |
| Project Type: | Transportation System Management and Operations |
| Description: | Install ramp meter, ramp detection, and cameras on NB Fourth Plain on ramp. |
| Termini: | I-5 at Fourth Plain |
| Project Length: | 0.15 miles |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $74,500 | $100,000 | June 1, 2027 | November 17, 2021 |
| Construction | $200,000 | $374,500 | July 1, 2022 | October 27, 2022 |
| Total | $274,500 | $474,500 |