Project Showcase
S 27th Street Shared Use Path
| Agency: | Washougal |
|---|---|
| Status: | Design |
| FHWA Aid#: | 7077(002) |
| Project Type: | Pedestrian & Bicycle Facilities |
| Description: | Construct dedicated separated shared use path. |
| Termini: | Index Street to Main Street |
| Project Length: | 0.53 miles |
| Federal Funds | Project Cost | Schedule | Obligation | |
|---|---|---|---|---|
| Preliminary Engineering | $224,000 | $224,000 | June 1, 2022 | July 12, 2022 |
| Right of Way | $216,250 | $250,000 | June 1, 2024 | |
| Construction | $600,000 | $1,443,500 | June 1, 2026 | |
| Total | $1,040,250 | $1,917,500 |
Project Photos